The forecasting department, traditionally reporting to the sale manager, has historically seen a forecast accuracy of about 60%, and this in turn causes problems for the following departments:
- 
Purchasing: What should we buy and how much?
 - 
Production: What should we really build?
 - 
Inventory management: We keep building the wrong thing.
 
The sales manager asked you to write her a memo, specifically addressing the following:
- 
How could you suggest that your new system would achieve any better levels of forecast accuracy?
 - 
Why is forecast accuracy itself not as important under traditional methods?
 - 
Create a chart or timeline that includes all of the following:
 - 
Which purchase orders have to be placed, and when
 - 
When manufacturing needs to begin, to have products delivered to a customer
 - 
Approximate dates for all of the following:
 - 
When the product must be shipped to meet the customer’s due date
 - 
When the application of the cover and packaging must take place to meet the customer’s due date
 - 
When the manufacturing of the widget must begin and end
 - 
When the raw material for the widget must be ordered
 - 
When the plastic cover must be ordered
 - 
When the cardboard box must be ordered
 - 
Includes notes explain your timing calculation
 - 
Assumes all of the following conditions:
 - 
The factory has two departments: manufacturing and packaging
 - 
Product X consists of 3 components
 - 
a widget manufactured in the factory with a total manufacturing lead time of 1 week
 - 
a plastic cover purchased from vendor A with a procurement lead time of 3 weeks
 - 
a cardboard shipping box purchased from vendor B with a procurement lead time of 4 weeks
 - 
The widget itself is made from steel (whose lead time from vendor C is 4 weeks).It takes 1 day for the cover to be applied to the product and for the product to be inserted in the box in the packaging department.
 - 
The shipping time to this customer is in 3 weeks, and you do not want it to be late or early. Assume you received the customer order on 3/31/2011
 - 
Ignore any holidays
 - 
Assume a 5-day work week
 - 
The customer requires the product to arrive at his location on 3/31/2011
 
								
															
															